Seasonal buoy tending

Fall buoy tending activities summary (Consolidated Chart)

Date of last update: February 09, 2010 9:23 loc

Small Craft Channels Planned Date
(Real Date)
P-1 - Lac Champlain (Baie Missisquoi) from Sep 28 to 29, 2009
(completed at 100%) (Sep 30, 2009)
P-2 - Rivière Richelieu, Amont de l'écluse Saint-Ours from Oct 05 to 09, 2009
(completed at 100%) (from Sep 29 to Oct 14, 2009)
P-3 - Rivière Richelieu, Aval de l'écluse Saint-Ours from Oct 13 to 14, 2009
(completed at 100%) (from Oct 15 to 20, 2009)
P-4 - Chenal de Lavaltrie from Oct 15 to 16, 2009
(completed at 100%) (from Oct 27 to 28, 2009)
P-5 - Chenal du Moine à Contrecoeur from Oct 19 to 23, 2009
(completed at 100%) (from Oct 22 to 29, 2009)
P-6 - Rivière Outaouais, Amont de l'écluse Carillon from Oct 06 to 08, 2009
(completed at 100%) (from Oct 05 to 07, 2009)
P-7 - Rivière Outaouais, Aval de l'écluse Carillon from Oct 08 to 14, 2009
(completed at 100%) (from Oct 07 to 09, 2009)
P-8 - Lac des Deux Montagnes et Rapides Lalemant from Oct 15 to 19, 2009
(completed at 100%) (from Oct 13 to 15, 2009)
P-9 - Rivière des Prairies Amont (Cheval Blanc) from Oct 20 to 23, 2009
(completed at 100%) (from Oct 16 to 20, 2009)
P-10 - Déversoirs, Chenal St-Pierre, Pointe-du-Lac from Oct 05 to 06, 2009
(completed at 100%) (from Oct 08 to 09, 2009)
P-11 - Chenal de Boucherville from Oct 07 to 09, 2009
(completed at 100%) (Oct 07, 2009)
P-12 - Lac Saint-Louis from Oct 13 to 19, 2009
(completed at 100%) (from Oct 13 to 21, 2009)
P-13 - Chenal de Repentigny from Oct 20 to 21, 2009
(completed at 100%) (from Oct 20 to 21, 2009)
P-14 - Rivière des Prairies Aval from Oct 22 to 23, 2009
(completed at 100%) (from Oct 21 to 23, 2009)
PC-1 - Entrepreneur Lac Memphrémagog from Oct 28 to 30, 2009
(completed at 100%) (Oct 20, 2009)